Stewart Engineering - Prime Consultant
Environmental Services, Inc. Natural Systems Investigation
S&ME - Geotechinial Investigations
URS Corporation - Traffic Engineering
Sungate Design Group - Hydraulics
The Notice to Proceed for this project was given in April. Construction preparation and mobilization is underway.
Construction Phase
The Neuse River Corridor is the central spine of the Capital Area Greenway, which was first adopted by the Raleigh City Council in 1976. In 1996, the City completed the Neuse River Regional Park Master Plan, which is a more detailed evaluation and proposal for the development of the Neuse River Corridor as a regional linear park.
The major recommendations of the Neuse River Plan include:
Since the adoption of the Neuse River Regional Park Master Plan in 1996, the City has acquired an interest in over 2,000 acres of land for park or greenway use along the river. This includes nine parcels of land that have been acquired for future parks along the corridor.
In 2007, the residents of Raleigh overwhelmingly approved a Parks and Recreation Bond Referendum that included $13 million for the development of the Neuse River Trail. The entire trail is 28 miles long and extends from Falls Lake Dam on Falls of Neuse Road to the Wake/Johnston County Line.
This segment of the Neuse River Trail extends from Poole Road to Anderson Point Park and is approximately 1.3 miles long. There is a major bridge crossing Crabtree Creek connecting to the existing trail in Anderson Point Park.
It is a goal of the Neuse River Regional Master Plan to complete an asphalt trail along the entire length of the Neuse River within Wake County. It is also a directive from the City Council to complete the trail by the end of 2012. This is one segment of that plan. Each of the segments is planned to be completed by 2012 and when complete the Neuse River will provide a connection between the primary greenway trails within Raleigh to Falls Lake, Wake Forest, Knightdale and Clayton.
Advertise for Construction: December 1, 2011
Open Bids: January 19, 2012
Award Bid: February 7, 2012
Begin Construction: April 2012
Completion: February 2013
The estimated cost of the project is $2.0 million