Lower Longview Stream Bank Repair

Last updated Nov. 21, 2017 - 1:40 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Stream Bank Repair
  • $200,000
  • Stormwater Management (Lead)
  • WK Dickson

Current Activity

Posted Tuesday, Nov. 21

The design plans for this stream bank repair project have been reviewed by the City's Development Services Department. Now, the environmental permitting process is taking place. Construction is expected to start in March 2018.

Summary

The primary goal of this project is to repair 500 feet of eroded stream bank running north of New Bern Avenue at Longview Lake Drive. Repairs will include:

  • Re-vegetating the stream to naturally stabilize it;
  • Lowering the slopes above the normal flow line of the creek;
  • Extending an existing stormwater pipe that goes to the creek in order to prevent erosion in the future; and
  • Protecting the outlet of the stream.

Schedule

Project schedule with dates and descriptions
DateDescription
Fall 2017Project design complete
Winter 2018Project construction begins
Spring 2018Project construction complete

History

This project is associated with additional efforts to restore Lower Longview Lake Dam