Optimist Park Playground Renovation

Last updated Nov. 13, 2017 - 9:49 am
  • Planning
  • Design
  • Construction
  • Completed
  • Park
  • $175,000
  • Midtown
  • Parks, Recreation and Cultural Resources (Lead)
  • Stewart Design

Current Activity

Due to unexpected site conditions discovered near the end of final design, the playground site has been relocated. Staff is currently working through final design and will begin construction during the Spring of 2018.

Summary

Each year funding is earmarked for the renovation of playgrounds throughout the city, and Optimist Park has been identified as the next priority project. A group of six volunteers representing the neighborhood has volunteered to assist in the design of the playground. Stewart Design is the landscape architecture consulting firm for the project.

Schedule

Project schedule with dates and descriptions
DateDescription
January 2017CAC Presentation
February 2017Playground Design Workshop
June 2017Final Design
July 2017Midtown CAC Final Design Presentation
Summer 2017Construction
Spring 2018Ribbon Cutting Ceremony

History

Optimist Park was built in 1973 and much of the existing playground equipment is original.