A section of the Blue Ridge Road plan map.

Transportation

Blue Ridge Road Widening Project

Our goal is to make Blue Ridge Road safe for all modes of transportation.

About the Project 

The purpose of this project is to provide a functional and safer multi-modal corridor for vehicles, cyclists, and pedestrians along the Blue Ridge Road corridor from Duraleigh Road to Crabtree Valley Avenue. We call this a Complete Street.

The project will widen a segment of Blue Ridge Road from Duraleigh Road to Crabtree Valley Avenue to three lanes with:

  • Curb and gutter;
  • Pedestrian culvert,
  • Sidewalks; and,
  • A multi-use path.

The City is receiving federal funding for a portion of this project.

What does that mean?

We are splitting the project into two sections for construction.

  • Blue Ridge Road South is from Duraleigh Road to just east of Homewood Banks Drive.
  • Blue Ridge Road North is from just east of Homewood Banks Drive to Crabtree Valley Avenue and is tentatively scheduled to begin construction in fall 2024.

Project Details

 
Type:
Streets
Budget:
$26.6 million
Project Lead:
Roadway Design & Construction
Contractors:
Carolina Sunrock LLC (Construction Contractor) and Kimley Horn (Design Consultant)

Upcoming Events

 
  • Apr
    24
    6p.m. • Wednesday

    Blue Ridge Road South - Pre-Construction Meeting

    Glen Eden Pilot Park
    Add to Calendar 2024-04-24 18:00:00 2024-04-24 19:00:00 Blue Ridge Road South - Pre-Construction Meeting We're holding a Pre-Construction Meeting! Where: Glen Eden Pilot Park, 1500 Glen Eden Drive, Raleigh, NC 27612When: April 24, 6-7 p.m. Construction will start on the Blue Ridge Road South Project this spring. Join us during the Pre-Construction Meeting to: Meet the construction team; Learn what to expect during construction; View traffic control plans; and, Ask construction related questions.  Glen Eden Pilot Park 1500 Glen Eden Drive Raleigh, NC 27612 City of Raleigh Project ManagerDennis Trujillodennis.trujillo@raleighnc.gov America/New_York public

Contact

 

Project Manager
Dennis Trujillo
dennis.trujillo@raleighnc.gov

Division Manager
Sylvester Percival, PE
Sylvester.Percival@raleighnc.gov

 

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

This project supports

Raleigh's Climate Plan in Action

Right of Way Acquisition

Updated Fall 2021

We are in the right-of-way and easement acquisition phase of the of the project.

Duke Energy is scheduled to start utility relocation work along the corridor in early 2022. Part of this work includes clearing along the corridor to allow for the relocation of utility poles. Utility relocation work is expected to take eight months. 

Next Steps

 

We are scheduled to advertise the project for construction in Spring 2022.

Lead Department:
Engineering Services

Construction

Blue Ridge Road South

We are holding a public Pre-Construction meeting! 

When: April 24, from 6-7 p.m.
Where: Glen Eden Community Center, 1500 Glen Eden Drive, Raleigh NC 

This will be a great opportunity to meet the construction team and learn what to expect during construction. 

City Council awarded the construction bid to Carolina Sunrock LLC. on March 5, 2024.

What's Next

Hold the Pre-Construction Meeting

Blue Ridge Road North

Duke Energy has finished their relocation activity along the northern part of the corridor. We are scheduled to advertise this section of the project for construction bids late this summer. 

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Lead Department:
Engineering Services

Southern Section Schedule

Date Activity
July 12, 2018 Early Designs Public Meeting (25% plan)
May 20, 2019 Advanced Design Public Meeting (65% Plan)
August 2019 City Council Presentation
June 2020 - December 2021 Right of Way and Easement Acquisition
Spring Through Fall 2023 Private Utility Relocation - Currently Ongoing
December 2023 & January 2024 Advertise for Construction Bids - Southern Section
April 24, 2024 Pre-Construction meeting
May 2024 Start Construction - Southern Section
Fall 2025 Project Completion - Southern Section

Northern Section Schedule

Date Activity
Fall 2022 - Fall 2023 Private Utility Relocation
Summer 2024 Advertise for Construction Bids - Northern Section
Late Summer 2024 Pre-Construction Public Meeting
Fall 2024 Start Construction - Northern Section
Fall 2025 Project Complete - Northern Section

Public Art

The project will include a public art component. Public art along this corridor will include stand-alone or integrated art, which may include a stand-alone sculpture, artwork sited at stormwater catchment site(s), and/or artwork integrated into pedestrian paving, lighting, benches/bike racks or other site elements. The artist will work closely with the design team, project stakeholders, and neighborhood groups to ensure a successful outcome. The artists selected for this project are Angelina Marino-Heidel and Joe Heidel.

Find out more about the public art coming to this project.

Project Details

The Blue Ridge Road Widening Project was prioritized in the Capital Improvement Program, as a major street project.

The roadway connects a major hospital and shopping center. Along with those two anchors, Blue Ridge is fronted by both single-family residences and apartment complexes. Towards the North-Eastern end, the road is intersected by a heavily used greenway. 

The project will widen Blue Ridge Road from Duraleigh Road to Crabtree Boulevard to a two-lane divided multimodal roadway.

While maintaining one lane of traffic in each direction, most of the project will include a center turn lane. There is one section with a large curve that will have a raised median. A sidewalk will be located on one side of the roadway and a multi-use path on the other, creating a connection to the House Creek Greenway. Transit stops will be improved along the corridor and made shelter-ready. There will also be a  pedestrian culvert under Blue Ridge Road that connects to House Creek Greenway.