Dorothea Drive Culvert Replacement

Last updated Nov. 06, 2017 - 11:44 am
  • Planning
  • Design
  • Construction
  • Completed
  • Culvert Replacement
  • TBD
  • Stormwater Management (Lead)
  • WK Dickson

Current Activity

Posted Monday, Nov. 6

This project is currently in the early design phase.

A public meeting was held on Wednesday, Nov. 1 to share the current design plans for the replacement of the aging storm drain on Dorothea Drive.

View the Public Meeting Presentation

If you have questions about this project or the public meeting, please contact Todd Rall, stormwater project manager, at 919-996-4006 or Todd.Rall@raleighnc.gov.

Summary

The intent of this project is to replace the culvert that runs under Dorothea Drive with a new, updated stormwater structure that will allow the stream to flow better and reduce localized flooding of the area. The project also will address and eliminate existing public utility concerns and allow this section of Dorothea Drive to meet current City street and sidewalk design standards.

Images

Dorothea Drive Culvert

Schedule

Project schedule with dates and descriptions
DateDescription
Winter 201870% design and easement acquisition complete
Spring 2018Environmental plans and project design complete
Summer 2018Construction bid prepared and awarded
Fall 2018Project construction begins
Spring 2019Project construction complete

History

Initially, repairs were made to the existing box culvert after City staff found sink holes at several locations along the culvert. It was determined after the repairs were made and the structure was further assessed that the culvert presents significant structural concerns and needs to be replaced.

Was this page helpful?

Forbes named Raleigh

7th - "America's Smartest Cities"

View our accolades >>