Knights Way Storm Drainage Improvements

Last updated Dec. 14, 2017 - 10:08 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Storm Drainage System
  • $3.5 million for North Ridge Phase IV & V
  • Stormwater Management (Lead)
  • Brown and Caldwell, Inc.

Current Activity

Posted Thursday, Dec. 14

This project is part of the North Ridge Phase IV and V storm drainage improvement and stream stabilization project. The City's design consultant, Brown and Caldwell, Inc., has completed surveying cross sections of the stream in the project area. Modeling updates are currently being done with the final project design expected to be complete in Spring 2018.

Summary

Project design for Knights Way includes the replacement of the existing 48-inch reinforced concrete pipe culvert under Knights Way with a box culvert that is 5 feet high and 12 feet wide in the vicinity of 1321 Knights Way and 7812 Blackwing Court. The culvert will outlet at the back of the property at 7812 Blackwing Court. Project location is noted in an overall project location map for the Northern North Ridge set of stormwater projects.

The goal of the project is to reduce structural flooding. In addition, Knights Way will be provided with a 25-year level of service. This means that the street will not overtop with water in a storm event of a magnitude expected to be equal or exceed once on average in a 25-year period.

Images

  • Upstream Culvert Headwall at Knights Way
  • Downstream Culvert Endwall at Knights Way

Schedule

Project schedule with dates and descriptions
DateDescription
Summer 2018Phase IV and V design complete
Fall 2018Permit requirements, easement acquisition, and coordination of private utility relocations complete
Winter 2019Phase IV and V construction begins
Winter 2020Phase IV and V construction complete

History

This project is one of several projects located along the northern tributary stream to the upper North Ridge Country Club Lake within the North Ridge community. It is located in the Perry Creek Watershed. A history of flooding events in the area resulted in public meetings in April and June 2006. An engineering study was completed in December 2006. Although there are no known structural flooding problems along the street the potential exists for the street to overtop with water. The engineering study recommended improvements to the existing undersized storm drainage system.

Was this page helpful?

WalletHub named Raleigh

Second Most Educated City

View our accolades >>