Parks and Greenway Bond Status

2014, 2007 and 2003 Bond Projects

Last updated May 12, 2016 - 8:47 am
Family walking

Raleigh voters approved bonds in 2003, 2007 and 2014 for parks and greenway projects.

For information regarding the 2014 Bond Projects, please view our brochure.

2014 Parks and Greenway Bond Projects

Project Name
StatusRecommended
Funding
Funding
Schedule
Greenway Development

Crabtree Creek Greenway WestDesign$ 4,400,0002015
Greenway ImprovementsPlanning$ 7,200,0002015-19
Greenway Connection Trenton RoadFuture$ 1,000,0002018-19
Lassiter Mill / Allegheny TrailFuture$ 2,000,000 2017-18
Land AcquisitionOngoing$ 10,000,000
Facility Upgrades

Playground ImprovementsOngoing
$ 1,500,0002015-19
Building ImprovementsOngoing
$ 2,025,0002015-19
Outdoor Security LightingOngoing
$ 4,000,0002015-18
ADA UpgradesOngoing
$ 2,000,0002015-18
New Facility/Redevelopment

Walnut Creek Softball ComplexPlanning
$ 5,000,0002015-16
Shelley Lake Comfort StationPlanning$ 500,0002015-16
Aquatic ImprovementsDesign
$ 8,000,0002015-19
Neighborhood ConnectionsPlanning$ 1,000,0002015-19
John Chavis Park ImprovementsPlanning$ 12,500,0002015-17
Historic Cemetery RestorationDesign$ 500,0002015
Lineberry Neighborhood Park
Design$ 1,250,0002015
Historic Property ImprovementsPlanning$ 1,000,0002015
Brentwood Park ImprovementsFuture$ 2,000,0002017-19
Apollo Heights Park ImprovementsFuture
$ 600,0002016-17
Kiwanis Park ImprovementsFuture
$ 700,0002016-17
Eastgate Park ImprovementsFuture
$ 600,0002016-17
Walnut Creek Wetland ParkFuture
$ 1,000,0002016-18
Laurel Hills Playground
Construction$ 1,000,000
2015
Pullen Art CenterPlanning$ 6,000,0002016-17
Baileywick Park Community CenterFuture
$ 12,000,0002017-19
Capital Blvd ImplementationFuture
$ 2,000,0002015
River Bend Park DevelopmentPlanning$ 2,000,0002015-17
TOTAL $ 91,775,000

For detailed funding schedule see the Adopted CIP FY2016-2020 page 62

See where the projects are located by using our interactive map.

2007 Parks and Greenway Bond Projects

Project Name
StatusRecommended Funding
Greenway Development

Honeycutt Creek GreenwayComplete$ 2,300,000
Crabtree Creek GreenwayComplete$ 6,588,721
Neuse River GreenwayComplete$ 13,000,000
Walnut Creek GreenwayComplete$ 3,000,000
Land AcquisitionPlanning$ 15,000,000
Unsatisfied Neighborhood Park Search AreasOn-going$ 3,000,000
Facility Upgrades

Playground ImprovementsComplete$ 878,222
Building ImprovementsComplete$ 1,750,000
Outdoor Security LightingComplete$ 239,825
Signage PackageComplete$ 300,000
New Facility/Redevelopment

Halifax Center ImprovementsComplete
$ 3,150,000
Jaycee Center ExpansionComplete$ 1,190,732
Barwell Road Park DevelopmentDesign
$ 1,700,000
Carolina Pines Center ExpansionComplete$ 700,000
Pullen Park Carriageway Bridge
$ 2,000,000
Chavis Park Carousel Building Adaptive Re-UsePlanning$ 500,000
Raleigh Senior Center
Complete$ 7,740,000
Annie Louise Wilkerson, MD Nature PreserveComplete$ 2,000,000
Mordecai Interpretive CenterComplete$ 1,562,500
Randleigh Farm
$ 400,000
Aquatics Facility - Buffaloe Road Aquatic CenterComplete$ 8,000,000
Abbotts Creek Community Center
(formerly Northeast Raleigh Community Center)
Complete
$ 9,000,000
Abbotts Creek Park
(formerly Northeast Raleigh Active Recreation Partnership)
Complete
$ 2,000,000
Lake Johnson Facility
Construction$ 2,600,000
TOTAL $ 88,600,00

2003 Parks and Greenway Bond Projects

Project Name
StatusRecommended Funding
Greenway Development

House Creek GreenwayComplete$ 1,495,000
Crabtree Creek GreenwayComplete$ 3,177,502
Honeycutt Creek GreenwayComplete$ 1,760,723
Chavis Way Extension
$ 23,000
Little Rock Trail ExtensionComplete$ 333,000
Walnut Creek GreenwayComplete$ 654,000
Neighborhood ConnectionsComplete$206,000
Upper Neuse River GreenwayComplete
$ 1,474,000
Land AcquisitionComplete$ 2,000,000
Facility Upgrades

Playground ImprovementsComplete$ 500,000
Building ImprovementsComplete$ 750,000
Outdoor Security LightingComplete$ 225,000
Mordecai Park RenovationComplete$ 325,000
Capacity Needs

Green Road Gym AdditionComplete$1,202,000
Lake Lynn Gym AdditionComplete$ 1,202,000
Optimist Pool ImprovementsComplete$ 4,195,313
Seasonal Pool ConversionComplete$ 455,000
New Facility/Redevelopment

Walnut Creek Environmental Ed. Ctr.Complete$ 2,060,000
Forest Ridge ParkConstruction$ 6,260,936
Marsh Creek Community CenterComplete$ 6,189,520
Neighborhood School Parks
$ 600,000
Chavis Park ImprovementsComplete$ 975,000
Pullen Park ImprovementsComplete$ 7,504,538
Brier Creek FacilityComplete$ 1,000,000
Hill Street Neighborhood Park
(formerly Timberlake)
Complete$ 2,192,756
Sanderford Road Neighborhood Ctr.Complete$ 1,300,000
Skate ParkComplete$ 520,000
Isabella Cannon Park Improvements
(formerly Gardner Street Park)
Complete$ 418,940
Neuse River Whitewater ParkDesign$ 195,000
TOTAL $49,194,288