Parks and Greenway Bond Status

2003 & 2007 Bond Projects

Last updated Apr. 06, 2015 - 3:28 pm

Raleigh voters approved bonds in 2003 and 2007 for parks and greenway projects.

2007 Parks and Greenway Bond Projects

Project Name
StatusRecommended Funding
Greenway Development

Honeycutt Creek GreenwayComplete$ 2,300,000
Crabtree Creek GreenwayComplete$ 6,588,721
Neuse River GreenwayComplete$ 13,000,000
Walnut Creek GreenwayComplete$ 3,000,000
Land AcquisitionPlanning$ 15,000,000
Unsatisfied Neighborhood Park Search AreasOn-going$ 3,000,000
Facility Upgrades

Playground ImprovementsComplete$ 878,222
Building ImprovementsComplete$ 1,750,000
Outdoor Security LightingComplete$ 239,825
Signage PackageComplete$ 300,000
New Facility/Redevelopment

Halifax Center ImprovementsComplete
$ 3,150,000
Jaycee Center ExpansionComplete$ 1,190,732
Barwell Road Park DevelopmentDesign
$ 1,700,000
Carolina Pines Center ExpansionComplete$ 700,000
Pullen Park Carriageway Bridge
$ 2,000,000
Chavis Park Carousel Building Adaptive Re-UsePlanning$ 500,000
Raleigh Senior Center
Complete$ 7,740,000
Annie Louise Wilkerson, MD Nature PreserveComplete$ 2,000,000
Mordecai Interpretive CenterComplete$ 1,562,500
Randleigh Farm
$ 400,000
Aquatics Facility - Buffaloe Road Aquatic CenterComplete$ 8,000,000
Abbotts Creek Community Center
(formerly Northeast Raleigh Community Center)
Construction
$ 9,000,000
Abbotts Creek Park
(formerly Northeast Raleigh Active Recreation Partnership)
Construction
$ 2,000,000
Lake Johnson Facility
Bidding
$ 2,600,000
TOTAL $ 88,600,00

2003 Parks and Greenway Bond Projects

Project Name
StatusRecommended Funding
Greenway Development

House Creek GreenwayComplete$ 1,495,000
Crabtree Creek GreenwayComplete$ 3,177,502
Honeycutt Creek GreenwayComplete$ 1,760,723
Chavis Way Extension
$ 23,000
Little Rock Trail ExtensionComplete$ 333,000
Walnut Creek GreenwayComplete$ 654,000
Neighborhood ConnectionsComplete$206,000
Upper Neuse River GreenwayComplete
$ 1,474,000
Land AcquisitionComplete$ 2,000,000
Facility Upgrades

Playground ImprovementsComplete$ 500,000
Building ImprovementsComplete$ 750,000
Outdoor Security LightingComplete$ 225,000
Mordecai Park RenovationComplete$ 325,000
Capacity Needs

Green Road Gym AdditionComplete$1,202,000
Lake Lynn Gym AdditionComplete$ 1,202,000
Optimist Pool ImprovementsComplete$ 4,195,313
Seasonal Pool ConversionComplete$ 455,000
New Facility/Redevelopment

Walnut Creek Environmental Ed. Ctr.Complete$ 2,060,000
Forest Ridge ParkDesign$ 6,260,936
Marsh Creek Community CenterComplete$ 6,189,520
Neighborhood School Parks
$ 600,000
Chavis Park ImprovementsComplete$ 975,000
Pullen Park ImprovementsComplete$ 7,504,538
Brier Creek FacilityComplete$ 1,000,000
Hill Street Neighborhood Park
(formerly Timberlake)
Complete$ 2,192,756
Sanderford Road Neighborhood Ctr.Complete$ 1,300,000
Skate ParkComplete$ 520,000
Isabella Cannon Park Improvements
(formerly Gardner Street Park)
Complete$ 418,940
Neuse River Whitewater ParkDesign$ 195,000
TOTAL $49,194,288