We are installing a new sidewalk!

The Inglewood Lane sidewalk project is the product of a successful petition the City received in the Winter of 2019.

The City plans to install a five foot sidewalk on the east side of Inglewood Lane between Manchester Drive and Yadkin Drive. 

Project Details

 
Type:
Sidewalks

Contact

 

Project manager
Diana Deadmore
diana.deadmore@raleighnc.gov
 

Division Manager
Sylvester Percival, PE
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Transportation
Participating Department:
Engineering Services
Service Unit:
Roadway Design and ConstructionMobility Strategy and Infrastructure

Subscribe

 

Planning

City Council has authorized staff to design and construct the sidewalk improvements as funding and staff resources become available.

The sidewalk project is currently awaiting funding allocation for the official design and construction. Project timeline scheduling has not been determined. If you have any questions or comments pertaining to this sidewalk improvement project please feel free to contact us via e-mail at Petition.Specialist@raleighnc.gov or by calling

919-996-4054.

 

 

Lead Department:
Transportation

Design

We have finished the early design plans and currently working on the advanced design plans.

We had a pop-up style meeting on the corner of Yadkin Drive and Inglewood Lane in late October.  City staff was on hand to show the design plans and answer questions about the project. 

Not able to attend the meeting? That's ok. Here is a presentation that explains the project.

Public Meeting Materials

 

Phase Contacts

 

Project Manager

Diana Deadmore

diana.deadmore@raleighnc.gov

Lead Department:
Engineering Services

Project Schedule

Activity Date
Public Meeting Oct. 25, 2023
Right of Way and Easement Acquisition Summer 2024
Start Construction Fall 2024
Project Completed Winter 2025