Rembert Drive without sidewalk

Transportation

Rembert Drive Sidewalk Project

We are making street improvements!

The Rembert Drive sidewalk project is the product of a successful petition the City received in the Fall of 2019. 

The new sidewalk is proposed to run along the north side of Rembert Drive from Winthrop Drive to Brookhaven Drive. 

Project Details

 
Type:
Sidewalks
Project Lead:
Transportation Planning

Contact

 

Project questions?
Comment Form

Lead Department:
Transportation
Participating Department:
Engineering Services
Service Unit:
Mobility Strategy and Infrastructure

Subscribe

 

Planning

City Council has authorized staff to design and construct the sidewalk improvements as funding and staff resources become available.

 

Lead Department:
Transportation

Design

Funding has been allocated for this project. We are hiring a consultant to design the project and plan to advertise the project for construction bids in summer 2024, with construction planned to begin in the fall. 

Lead Department:
Engineering Services

Project Schedule
Date  Activity
Start Design  Winter 2024
Design Meeting  Spring 2024
Advertise for Construction Contracts Summer 2024
Start Construction  Fall 2024
Project Complete Early Winter 2025