MyRaleigh

Old Wake Forest Road Widening Project

Last updated Nov. 29, 2017 - 11:15 am
  • Planning
  • Design
  • Construction
  • Completed
  • Street Improvement Project
  • 4.8 Million
  • Roadway Design and Construction (Lead)
  • Wetherill Engineering, INC.

Current Activity

Posted November 2017

The design phase has begun the first public meeting is tentatively scheduled for January 2018.

Summary

The project will widen Old Wake Forest Road to a 4-lane divided roadway from Atlantic Avenue/Litchford Road to capital Boulevard (US1). Roadway improvements will include:

  • Curb and gutter
  • Sidewalks on both sides of the roadway
  • Bicycle lanes
  • Streetlights
  • Landscaping
  • New railroad bridge

Schedule

Project schedule with dates and descriptions
DateDescription
January 2018Public Meeting - 25% Plan
Spring 2018Public Meeting - 65% Plan
Late Spring 2018Public Hearing
Winter 2019Complete Right of Way and Easement Acquisition
Winter 2019Advertise for Construction Contract
Spring 2019Award Construction Contract
Summer 2021Project Completion

History

The Old Wake Forest Road Widening Project was partially funded by the 2013 Transportation Bond referendum.

Was this page helpful?

Money Magazine named Raleigh

A Top Retirement City

View our accolades >>