Yonkers Road Improvements Project

Last updated Sep. 26, 2017 - 10:45 am
  • Planning
  • Design
  • Construction
  • Completed
  • Street Improvement Project
  • $2,500,000
  • Roadway Design and Construction (Lead)
  • RK&K (Consultant)

Current Activity

Currently, the design consultant is working on the 65 percent plans, and a public meeting is tentatively scheduled for November 2017.

Summary

This project will reconstruct the existing roadway to a 2-lane curb and gutter section with bike lanes and sidewalk on the south side from Capital Boulevard to New Bern Avenue.

Schedule

Project schedule with dates and descriptions
DateDescription
May 12, 2016Public Meeting
Fall 2017Public Meeting
Winter 2018Public Hearing
Summer 2018Complete Right of Way Acquisition
Summer 2018Advertise for Construction Contract
Fall 2018Award Construction Contract
Fall 2020Project Complete

History

The roadway pavement and structure along Yonkers Road is in a degraded condition and needs to be repaired and rehabilitated to provide an overall safer and structurally sound corridor for traveling.