Current Activity

Stormwater design plans are complete and have gone through the plan review process. Project construction is expected to start in October. 

Note: This project is being incorporated into the Public Utilities Department's project to upgrade/relocate sanitary sewer and water lines along Alexander Road.

Summary

The purpose of this project is to replace failing public drainage pipes and structures and add new structures within the street right-of-way.

Images

Alexander Road & McCarthy Street Intersection

Schedule

Project schedule with dates and descriptions
DateDescription
Winter 2017Expected bid and award complete
Fall 2017Project construction begins
Spring 2018Project construction complete

History

This project will provide upgrades to the public drainage system near the intersection of Alexander Road and McCarthy Street.