Peace Street West Streetscape

Last updated Nov. 26, 2018 - 11:52 am
  • Planning
  • Design
  • Construction
  • Completed
  • Streetscape Project
  • $2.2 Million
  • Roadway Design and Construction (Lead)
  • Design Consultant - Cole, Jenest, & Stone

Current Activity

Updated Nov. 20

The project is scheduled to advertise for construction bids in Feb. 2019.

Summary

The Peace Street West project will consist of streetscape improvements between Saint Mary's Street and West Street.

The project will include:

  • New brick paver sidewalks along both sides of the corridor;
  • Street trees with grates;
  • Pedestrian ramp upgrades;
  • Traffic signal upgrades with mast arms;
  • Driveway consolidation; and,
  • Undergrounding of some overhead utility lines along the corridor.

Images

  • *St. Mary's Street Intersection St. Mary's Street Intersection
  • *Gaston St to Boylan St Gaston St to Boylan St
  • *Boylan Street to Glenwood Ave Boylan Street to Glenwood Ave
  • *Glenwood Ave to West St Glenwood Ave to West St

Schedule

Project schedule with dates and descriptions
DateDescription
February 5, 2015Public Design Meeting
Spring 2017City Council Presentation
Feb. 2019Right of Way and Easement Acquisition
Feb. 2019Advertise Construction Contract
April 2019Award Construction Contract
May 2020Complete Construction

History

Peace Street west was previously placed on hold to wait for funding to cover right of way acquisition and construction. The project was recently included in the 2013-2014 Capital Improvement Program, completing the remaining funding necessary to proceed with the project.