Current Activity

Posted Wednesday, June 13

This project is complete. The stormwater drains near the intersection of Alexander Road and McCarthy Street have been repaired. This project also was incorporated into the Public Utilities Department's upgrade/relocation of sanitary sewer and water lines along Alexander Road. Questions on the public utilities part of this project can be directed to Louis Bennett at Louis.Bennett@raleighnc.gov or 919-996-3504.

Summary

The purpose of this project is to replace failing public drainage pipes and structures and add new structures within the street right-of-way.

Images

Alexander Road & McCarthy Street Intersection

Schedule

Project schedule with dates and descriptions
DateDescription
Winter 2017Expected bid and award complete
Winter 2018Project construction began
Spring 2018Project construction complete

History

This project will provide upgrades to the public drainage system near the intersection of Alexander Road and McCarthy Street.