Lower Longview Lake Dam Rehabilitation

Last updated Oct. 26, 2018 - 12:07 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Lake & Dam Rehabilitation
  • $3.4 million
  • Stormwater Management (Lead)
  • D.H. Griffin Infrastructure, LLC
  • Schnabel Engineering

Current Activity

Posted Friday, October 26

This project is almost complete. The contractor finished constructing the dam and rebuilding the road that goes over the dam. Partial dredging of the two reservoirs in the lake is underway. Project construction is scheduled to be finished this fall. The construction timeframe may shift slightly due to additional work required following a water main break in the area on Oct. 23. 

Albemarle Avenue will remain closed until construction is complete - Vehicle and foot traffic is not permitted in areas directly surrounding the bridge. Please use designated detours. Work hours will be Monday through Friday from 7 a.m. to 6 p.m. with no work scheduled on the weekend except in an emergency or with prior approval from the City.

If you have any questions about upcoming construction, contact Gilles Bellot, PE, at Gilles.Bellot@raleighnc.gov or 919-996-4001.

Watch drone footage of the project during construction:



Watch Dam Rebuild of Lower Lake Longview:

Summary

The dam and spillway rehabilitation project for Lower Longview Lake went to bid in August 2016 with five proposals received on Sept. 12, 2016. There is an 18-month construction period to make necessary improvements to the dam and ensure that the area surrounding Albemarle Avenue is safe.

Images

  • *Construction of the emergency spillway and road at Lower Longview Lake Dam Construction of the emergency spillway and road at Lower Longview Lake Dam
  • *Construction of the emergency spillway for Lower Longview Lake Dam Construction of the emergency spillway for Lower Longview Lake Dam
  • *Construction of the emergency spillway for Lower Longview Lake Dam Construction of the emergency spillway for Lower Longview Lake Dam
  • *Temporary cofferdam put in place for construction Temporary cofferdam put in place for construction
  • *Preparing for construction Preparing for construction

Schedule

Project schedule with dates and descriptions
DateDescription
Fall 2016Project bid received and project presented to City Council
Spring 2017 Project construction began
Fall 2018Project construction complete

History

The City of Raleigh approved the rehabilitation of Lower Longview Lake as a Capital Improvement Program (CIP) project in 2008. In 2009, Albemarle Avenue was closed at the dam due to deterioration of the bridge superstructure, which has caused the bridge to be unsafe for vehicle traffic. Instead of approaching the project with a temporary repair to the bridge, City staff has established a more sustainable and long-lasting design. Albemarle Avenue will remain closed until the dam rehabilitation project is complete.