Swann Street Drainage Improvements Phase I

Last updated Jun. 13, 2018 - 12:05 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Storm Drainage System
  • $1.5 million
  • Stormwater Management (Lead)
  • WK Dickson (Design)
  • North State Environmental, Inc. (Construction)

Current Activity

Posted Wednesday, June 13

The consultant has completed the project design and received necessary environmental permits for construction. The construction contract was awarded by Raleigh City Council on May 15 to North State Environmental, Inc. It will take 30 to 45 days to carry out the contract. Construction will start in late June or July and will last about six months. This timeframe may vary due to weather, unanticipated utility needs, and other construction factors. Residents who live directly in the construction area may experience traffic detours as well as temporary disruptions to water, gas, phone, and cable services.

If you have any questions about upcoming construction, contact David Kiker, PE, at David.Kiker@raleighnc.gov or 919-996-4074.

Summary

The primary project goals are to eliminate roadway flooding in the 10-year flood event and to minimize any flooding to insurable structures within the project area. 

Sustainability

Phase I design plans are intended to make proposed drainage improvements while ensuring that erosion in this area does not get worse. Bank stabilization to minimize erosion and property loss will be addressed in Phase II of this project. Proposed solutions include using several boulder cross vanes to reduce the slope and velocities of the stream channel and adding a large concrete vault with a four foot drop to help reduce the strength of storm flows.

Images

  • Swann Street Flooding
  • Swann Street Overflow
  • Swann Street Drainage

Schedule

Project schedule with dates and descriptions
DateDescription
Fall 201670% design plans and finalized easement plans completed
Spring 201790% design plans completed
Summer 2017Drainage easements and environmental permit process complete
Fall 2017Project design complete
Winter 2018Project bid complete
Summer 2018Project construction begins
Winter 2019Project construction complete

History

The Stormwater Management Division completed a drainage basin study in 2013 for the Swann Street area. Recommendations were provided to reduce the frequency of flooding, roadway and driveway overtopping, and complete bank erosion stabilization. Raleigh City Council approved the design phase of the Swann Street Drainage Improvement Project – Phase I in July 2015. This project will be divided into two phases with Phase I focusing on the downstream improvements and Phase II on the upstream improvements.