Current Activity

Posted Friday, Nov. 9

Engineering Construction Company was awarded the construction contract for this project. Renovations to the fire house will start in late fall.

Summary

The purpose of this project is to make necessary renovations to Fire Station 11, which will include making improvements to the dormitory bay and bathrooms along with the dayroom bay. Renovations to the dayroom bay include the kitchen and watch room as well as expanding the two equipment bays to accommodate a larger ladder truck. Expansion of the equipment bays may include increasing the bay height.

Images

Fire Station 11 Rendering

Schedule

Project schedule with dates and descriptions
DateDescription
Spring 2017Project design begins
Summer 2018Project design complete
Late Fall 2018 Project construction begins
Late Fall 2019Project construction complete

History

Completing renovations to Fire Station 11 will help enhance the functionality of the station and allow for it to continually meet the growing needs of its service area.