Adopted Capital Improvement Program FY2015 - FY2019 - page 38

CITY OF RALEIGH
ADOPTED CIP FY2015-2019
Little River Projects
Wake County, in partnership with the City of Raleigh and the utility merger municipalities, has worked for
many years to acquire the land necessary to construct the Little River Reservoir in Eastern Wake County.
The Little River water shed is the last available water shed in Wake County that is economically feasible
to develop as a reservoir. The City of Raleigh Water Supply plan identifies the Little River Reservoir as
the long range source of new drinking water for the Greater Raleigh Utility Service Area. This project
grouping funds the wetland mitigation cost and wetland restoration areas.
Little River Projects
FY 2015
FY 2016
FY 2017
FY 2018
FY 2019 5 Year Total
FY 2020 to FY
2024
10 Year Total
County Acquisition
Reimbursement
500,000
500,000
500,000
500,000
500,000
2,500,000
2,500,000
5,000,000
Property Acquisition
-
2,500,000
2,500,000
2,500,000
2,500,000
10,000,000
12,500,000
22,500,000
Construction
-
-
-
-
-
-
15,600,000
15,600,000
Mitigation Monitoring
-
-
-
-
-
-
300,000
300,000
Subtotal
500,000
$
3,000,000
3,000,000
3,000,000
3,000,000
12,500,000
30,900,000
43,400,000
Highlighted Project
Little River County Acquisition Reimbursement $5,000,000
Wake County, in partnership with the City of Raleigh and
the utility merger communities, has worked for many years
to acquire the land necessary for the construction of the
Little River Reservoir in Eastern Wake County. Because
of jurisdictional issues, Wake County has managed all land
acquisition. This project fulfills a contractual obligation to
reimburse the County.