33 Water Pipe (linear feet) Services (each) Insertion Valve (each) Fire Hydrants (each) Diameter Total Bore and Jack Diameter Each Diameter Each Each 6” $102.76 $171.37 3/4” $1,086.83 2” $4,280.07 $4,175.17 8” $106.16 $213.95 1” $1,135.23 4” $7,810.27 12” $130.66 $374.93 2” $6,001.44 6” $10,164.78 16” $174.92 $481.91 8” $12,518.25 24” $183.89 $588.89 12” $17,226.22 Fee Schedule Ord No. 2018-846 (Section 8-2096(f)) Sewer Pipe (linear feet) Manholes (each) Services Diameter Depth Bore and Jack Diameter Depth (Each) 0-16 16+ 0-16 16+ 8” $120.03 $159.05 $421.98 4’ $3,237.16 $7,566.23 $1,593.00 12” $127.47 $167.65 $583.98 5’ $7,062.90 $9,929.10 16” $132.82 $175.12 $954.37 6’ $11,204.10 $19,341.67 18” $141.84 $184.15 $1,324.73 24” $170.96 $215.38 $1,666.72 Bypass Pumping Rock Asphalt Per 150 If <10 CY (LS) additional (CY) per LF of sewer main 8” 12” 16” 24” $8,573.29 $11,904.19 $15,750.27 $15,750.27 $1,283.96 $58.85 $40.68