Yonkers Road Improvements Project

Last updated Mar. 16, 2018 - 3:35 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Street Improvement Project
  • $2,500,000
  • Roadway Design and Construction (Lead)
  • RK&K (Consultant)

Current Activity

Posted Monday, Feb. 16

Currently, the design consultant is working on the 65 percent plans, and a public meeting is tentatively scheduled for March.


This project will reconstruct the roadway to a two-lane, curb-and-gutter section with bike lanes and sidewalk on the south side from Capital Boulevard to New Bern Avenue.


Project schedule with dates and descriptions
May 12, 2016Public Meeting
April 2018Public Meeting
Spring 2018Public Hearing
Winter 2019Complete Right of Way Acquisition
Winter 2019Advertise for Construction Contract
Late Winter 2019Award Construction Contract
Late Spring 2021Project Complete


The pavement along Yonkers Road has degraded and needs to be repaired to provide a more structurally sound corridor.