MyRaleigh

Juniper Street Stormwater Project

Last updated Feb. 06, 2019 - 9:25 am
  • Planning
  • Design
  • Construction
  • Completed
  • Storm Drainage System
  • TBD
  • Stormwater Management (Lead)
  • Hazen and Sawyer

Current Activity

Posted Friday, Feb. 1

The consultant finished the design for this project. We are getting permits and easements from property owners that are needed to complete this project. We're on schedule to start construction in the spring.

Findings from the Laurel Hills Area Watershed Study led to this project. You can request a copy by calling 919-996-3940 or RaleighStormwater@raleighnc.gov.

Summary

The purpose of this project is to address street flooding that is occurring on Juniper Street in the public right-of-way (areas that are considered public property).

Schedule

Project schedule with dates and descriptions
DateDescription
Fall 2017 - Spring 2018Project planning period
Late Fall 2018Project design complete
Winter 2019Permitting process complete
Spring 2019Easement acquisition and construction bid complete; Construction starts
Early Summer 2019Project construction complete

History

The drainage issue on Juniper Street was identified as a project following findings from the Laurel Hills Area Watershed Study. The project was evaluated as a high priority project using the Stormwater Management Division's prioritization model, which ranks projects based on its severity and need to address the stormwater issue.