New Hope Church Road Widening Project

Last updated Oct. 23, 2018 - 9:41 am
  • Planning
  • Design
  • Construction
  • Completed
  • Street Improvement Project
  • 5.4 Million
  • Roadway Design and Construction (Lead)
  • Ramey Kemp & Associates

Current Activity

updated Aug. 31

The project is in the right of way and easement acquisition phase. The City is on schedule to advertise the project for construction bids in the late fall of 2018.

Summary

The improvements will include new pavement and restriping between Green Road and Ingram Drive and will widen the roadway from Ingram Drive to Deana Lane. The enhancements will include:

  • A three-lane, curb-and-gutter section;
  • Bike lanes;
  • Sidewalk on both sides of the street;
  • Stormwater and erosion control; and,
  • Culvert replacement

Assessments for new curb and gutter installation will be applicable according to City of Raleigh Assessment Policies. Residential statutory costs are $32 per linear foot and commercial statutory costs are $64 per linear foot.

Schedule

Project schedule with dates and descriptions
DateDescription
November 29, 2016Preliminary Plans Public Meeting (25% plan)
November 29, 2017Design Plan Public Meeting (65% Plan)
Late Summer 2018Complete Right of Way and Easement Acquisition
Late Fall 2018Advertise for Construction Contract
Winter 2019Award Construction Contract
Late Summer 2020Project Completion

History

The New Hope Church Road Widening Project was prioritized in the Capital Improvement Program as a major street project.