Brockton Drive Dam
- Planning
- Design
- Construction
- Completed
- Lake & Dam Preservation
- Approximately $4.5 million
- Stormwater Management (Lead)
- CDM Smith, Inc.
- Carolina Civil Works, Inc.
- Public Utilities Department
Current Activity
Posted Friday, April 6
Construction for the first phase of this project, which has been contracted to Carolina Civil Works, Inc., is underway. Construction includes draining the lake, replacing storm drainage and sanitary sewers, and re-grading the upper lake on Brockton Drive. Major construction, including the demolition of the upper lake, began in August after the lake was completely drained.
For your safety, residents are not permitted to enter the construction site. Work hours will be Monday through Friday from 7:30 a.m. to 5:30 p.m. with no work scheduled on the weekend or City holidays except in an emergency or with prior approval from the City.
If you have any questions about upcoming construction, contact Todd Rall, at 919-996-4006 or Todd.Rall@raleighnc.gov.
Summary
This project will provide dam and storm drainage improvements at the Brockton Drive dam by addressing dam safety concerns, reducing the frequency and severity of flooding in adjacent structures, and improving water quality, while remaining consistent with the City of Raleigh's Lake Preservation policy.
The Brockton Drive Lake and Dam Rehabilitation will be completed in two phases:
Phase I - Upper Dam: This phase includes removing the upper lake to restore the channel at Brockton Drive and increasing the size of the existing drainage pipe with a box culvert. Stream restriction at the downstream corner of Walden Woods Club House pool will be removed. The stream also will be stabilized and reshaped with plants/vegetation at the upper stream channel.
Phase II - Lower Dam: The spillway structure on the lower dam will be replaced and then the lower dam will be replaced with a roller-compacted concrete structure.
Images
Schedule
Date | Description |
Summer 2016 | Bid proposal, Phase I design, easements acquisition, and private utility coordination complete |
Fall 2016 | Phase I bid and award complete |
Summer 2017 | Phase I construction begins |
Winter 2018 | Phase II design complete |
Winter 2018 | Phase I construction complete (Planting to possibly take place in Fall 2018) |
Spring 2018 | Phase II construction bid complete |
Summer 2018 | Phase II construction bid awarded |
Fall 2018 | Phase II construction begins |
Fall 2019 | Phase II construction complete |
History
The existing spillway for the upper lake at Brockton Drive is currently in very poor condition. The upper lake collects debris and, in intense storms, floods adjacent structures, which are occupied. The lower lake dam spillway is undersized and there is severe erosion at the outlet.