Juniper Street Stormwater Project

Last updated Nov. 09, 2018 - 10:21 am
  • Planning
  • Design
  • Construction
  • Completed
  • Storm Drainage System
  • TBD
  • Stormwater Management (Lead)
  • Hazen and Sawyer

Current Activity

Posted Friday, Nov. 9

The consultant is working on the final design for this project and obtaining easements from property owners that are required to complete this project.

The Laurel Hills Area Stormwater Management Study provides more information about the watershed study that led to this project.

Summary

The purpose of this project is to address street flooding that is occurring on Juniper Street in the public right-of-way (areas that are considered public property). 

Schedule

Project schedule with dates and descriptions
DateDescription
Fall 2017Project planning period
Fall 2018Project design complete
Fall 2018Easement acquisition and permitting process complete
Winter 2019Construction bid prepared and awarded
Winter 2019Project construction begins
Spring 2019Project construction complete

History

The drainage issue on Juniper Street was identified as a project following findings from the Laurel Hills Drainage Area Study. The project was evaluated as a high priority project using the Stormwater Management Division's prioritization model, which ranks projects based on its severity and need to address the stormwater issue.