Upper Audubon & Wagram Court Stream Stabilization

Last updated Nov. 07, 2018 - 11:22 am
  • Planning
  • Design
  • Construction
  • Completed
  • Storm Drainage System & Stream Stabilization
  • $3.5 million for North Ridge Phase IV & V
  • Stormwater Management (Lead)
  • Brown and Caldwell, Inc.

Current Activity

This project is part of the North Ridge Phase IV and V storm drainage improvement and stream stabilization project. The design consultant, Brown and Caldwell, Inc., is working on finalizing the design plans. Plans will be completed after all necessary easements are received from specific properties that are in the project area. These residents have been notified and staking of the easement limits has been completed.

Required permits have been received from the North Carolina Department of Environmental Quality and the US Army Corp of Engineers. Brown and Caldwell, Inc. is in the process of getting necessary permits from the City of Raleigh.

The City also is working with private utility companies to relocate utilities in the project area.

All necessary easements, permits, and private utility relocations will need to take place before construction can begin.

If you have questions about this project or the easement acquisition process, contact Carrie Mitchell, PE, at 919-996-4068 or Carrie.Mitchell@raleighnc.gov.

Summary

Project design for Upper Audubon Drive and Wagram Court includes the installation/replacement of a 24-inch pipe near 7109 Laketree Drive and 7901/7905 Audubon Drive. A portion of the stormwater flow will be routed through a new 24-inch stormwater pipe system along Wagram Court.

In addition, approximately 1,200 feet of stream between Rainwood Lane and Knights Way and an additional 280 feet of stream downstream of Knights Way will be stabilized to accommodate the streams 10-year storm event flows in the North Ridge community.

Images

  • North Ridge Stream 1
  • North Ridge Stream 2

Schedule

Project schedule with dates and descriptions
DateDescription
Winter 2019Phase IV and V design complete
Winter 2019Permit requirements, easement acquisition, and coordination of private utility relocations complete
Spring 2019Phase IV and V construction begins
Summer 2020Phase IV and V construction complete

History

This project is located along a stream near North Ridge Country Club Lake within the North Ridge community. It is located in the Perry Creek Watershed. A history of flooding events in the area resulted in public meetings in April and June 2006. An engineering study was completed in December 2006. The engineering study recommended improvements to the existing undersized storm drainage system. Phases one through three have been completed.

Was this page helpful?

Cheapism.com named Raleigh

Among America's Six Fastest Growing and Most Affordable Cities

View our accolades >>