New bridges are being designed to replace the existing Structures 17 and 19 on the Shelley Lake Loop Trail.

Project Details

 
Type:
Greenways and Trails
Budget:
$454,000
Contractors:
Alpha & Omega

Contact

 

Lisa Schiffbauer

Lead Department:
Parks, Recreation and Cultural Resources

Subscribe

 

Planning

This phase is complete.

Design

The City is consulting with Alpha & Omega to design repairs and replacement of two pedestrian structures at Shelley Lake Loop Trail. However, due to current plans by the City of Raleigh Public Utilities Department to begin a sewer utility replacement project these bridge repairs and replacements are on hold to better coincide with the sewer construction project schedule.

Construction

Phase details coming soon.

Complete

Phase details coming soon.


History

The Capital Area Greenway System was first adopted by City Council in 1976. This plan proposed a system of linear parks located primarily along rivers, streams, and creeks, and included the opportunity for an interconnected system of pedestrian trails across the region.

Schedule

Date Activity
On-Going Design
TBD Construction