Blue Ridge Road Widening Project

Last updated Apr. 18, 2018 - 9:45 am
  • Planning
  • Design
  • Construction
  • Completed
  • Road Widening
  • 12,000,000
  • Roadway Design and Construction (Lead)
  • Kimley Horn (Design Consultant)

Current Activity

Updated March 26

The project is in the early design phase. The design consultant (Kimley Horn) is completing surveys and collecting data along the corridor. A Preliminary Plan Public Meeting is tentatively planned for June.

Summary

The project will widen a segment of Blue Ridge Road from Duraleigh Road to Crabtree Valley Avenue to three lanes with;

  • Curb and gutter
  • Sidewalks on both sides of the roadway; and,
  • Bicycle lanes.

Schedule

Project schedule with dates and descriptions
DateDescription
June 2018Preliminary Plans Public Meeting (25% plan)
Fall 2018Design Plan Public Meeting (65% Plan)
Fall 2019Complete Right of Way and Easement Acquisition
Fall 2019Advertise for Construction Bids
Winter 2020Award Construction Contract
Spring 2022Project Completion

History

The Blue Ridge Road Widening Project was prioritized in the Capital Improvement Program, as a major street project.

Was this page helpful?

NerdWallet named Raleigh

Among the Most Innovative Tech Hubs in the Nation

View our accolades >>