Sandy Forks Road Widening Project

Last updated Feb. 21, 2017 - 12:25 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Road Widening Project
  • $9.9 million
  • North
  • Roadway Design and Construction (Lead)
  • RK&K (Design Consultant)
  • Carolina Sunrock, LLC (Construction Contractors)

Current Activity

Construction Update, Tuesday, February 21, 2017

The installation of street lights continues north of the Lynn Road/ Spring Forest Road intersection running towards Falls of Neuse Road. Street trees are also being installed along the corridor in locations where sidewalks are completed. The entrance to the Brookhollow Subdivision was recently completed and traffic placed into its final configuration, providing safer ingress/egress for vehicular and pedestrian traffic.

Contractors continue the installation of storm drains, curb and gutter, asphalt, and sidewalks along the north side of Sandy Forks Road between Suburban Drive and Falls of Neuse Road.

The next step in the project is to complete the last temporary road closure (one short block between Falls Neuse Shopping Center and the Falls of Neuse Road intersection). During the two-week shutdown, the entire block will be removed and replaced (and grade slightly lowered to improve sight distance and safety approaching the intersection), as well as installing a new storm drainage system. The temporary road closure of this block is currently anticipated to begin in mid-March (weather permitting).

Following completion of the temporary road closure, traffic will be shifted into a new pattern to the outsides of the roadway from Six Forks Road to Falls of Neuse Road so the contractor may shift their focus to finalizing all median work along the corridor. This will constitute the final phase of construction and will include construction of a bioretention stormwater treatment facility in the median of Sandy Forks Road between Shanda Drive and The Lakes Drive. Once median work is completed around May, then the contractor will prepare for final paving operations along the entire corridor.

The Sandy Forks Road Widening Project was featured on The Raleigh Television Network’s show, Under Construction.

You can also keep up to date on City of Raleigh street and sidewalk projects on Twitter and Facebook.

Summary

The objectives of the project are to replace the failing pavement and improve safety and mobility for all users, including motorists, pedestrians, and bicyclists.

The project will include:

  • Replacement of the existing pavement
  • Widening the roadway
  • Construction of a center turn-lane
  • Landscaped median
  • Additional left-turn lanes
  • Bicycle lanes
  • Sidewalks

In addition, reconfiguring the intersection at Sandy Forks Road and Lynn/Spring Forest Road will reduce congestion.

Sustainable features of this project include:

  • Three bioretention areas
  • Native landscaping
  • Bike & pedestrian access
  • Context‐sensitive solutions
  • Cultural outreach
  • Warm mix asphalt/recycled asphalt

Sustainability logo

In February 2014 City Council authorized staff to register this project into the Greenroads program. The Greenroads Rating System is a sustainability rating system for roadway design and construction projects. Greenroads was established in 2010 and is a very similar process to the LEED certification program for building projects. Since many of the current plan initiatives for this project are in line with credits associated with the Greenroads rating system, it is believed the Sandy Forks Road project would be a good candidate to consider for the program. Using Sandy Forks Road as a pilot project in the program will provide staff with additional knowledge and familiarity with the latest sustainable transportation design best practices that would benefit the City’s approach to future roadway projects. A copy of the Greenroads presentation can be found under Public Meeting information on the right side of this page.

This project includes three water treatment devices (bioretention areas), including the first public roadway median bioretention area to be installed by the City of Raleigh. Installation of the three bioretention areas will treat stormwater runoff to reduce erosion and increase water quality to the downstream watershed. The project also includes 5' bicycle lanes and 6' sidewalks along both sides of the roadway to provide accommodations for both pedestrians and bicyclists. A landscaping plan will be incorporated into the project and Duke Progress Energy will provide a street lighting plan with the use of LED fixtures to reduce energy costs along the completed corridor.

Images

  • Visualization of Sandy Forks Road
  • Typical Section 1 - 3 Lane Undivided
  • Typical Section 2 - 2 Lane Divided
  • Street Trees and Plantings Template
  • Existing Sandy Forks Road

Schedule

Project schedule with dates and descriptions
DateDescription
December 5, 2013Corridor Public Meeting (25% Design)
April 10, 2014Design Public Meeting #1 - (65% Design)
May 13, 2014Design Public Meeting #2 - (65% Design)
July 1, 2014 (evening session)Public Hearing at City Council
July 21, 2015Completed Right of Way Acquisition
July 27, 2015Advertised Construction Contract
November 3, 2015 Award Construction Contract
January 8, 2016Notice to Proceed With Construction
January - March 2016Erosion Control, and Clearing
April 2016 - October 2016 Road Widening, Sidewalks and Curb & Gutter
November 2016 - April 2017 Median Construction and Final Paving
June 2017Landscaping
July 2017Project Completion

History

Sandy Forks Road is classified as a two-lane divided avenue in the City of Raleigh's Comprehensive Transportation Plan and carries an average of 9,000 - 13,000 vehicles per day (estimate). This project design was approved by Council at the September 4, 2012 meeting. The project will improve traffic capacity and congestion, pedestrian connectivity, safety, and provide a multi-modal solution between the residential and retail/business districts at each end of the corridor.

Was this page helpful?

NerdWallet named Raleigh

Among the Most Innovative Tech Hubs in the Nation

View our accolades >>