Yonkers Road Improvements Project

Last updated Nov. 29, 2017 - 10:55 am
  • Planning
  • Design
  • Construction
  • Completed
  • Street Improvement Project
  • $2,500,000
  • Roadway Design and Construction (Lead)
  • RK&K (Consultant)

Current Activity

Currently, the design consultant is working on the 65 percent plans, and a public meeting is tentatively scheduled for January 2018.

Summary

This project will reconstruct the existing roadway to a 2-lane curb and gutter section with bike lanes and sidewalk on the south side from Capital Boulevard to New Bern Avenue.

Schedule

Project schedule with dates and descriptions
DateDescription
May 12, 2016Public Meeting
Winter 2018Public Meeting
Late Winter 2018Public Hearing
Late Summer 2018Complete Right of Way Acquisition
Late Summer 2018Advertise for Construction Contract
Winter 2019Award Construction Contract
Spring 2021Project Complete

History

The roadway pavement and structure along Yonkers Road is in a degraded condition and needs to be repaired and rehabilitated to provide an overall safer and structurally sound corridor for traveling.