Yonkers Road Improvements Project

Last updated Jan. 11, 2018 - 2:13 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Street Improvement Project
  • $2,500,000
  • Roadway Design and Construction (Lead)
  • RK&K (Consultant)

Current Activity

Currently, the design consultant is working on the 65 percent plans, and a public meeting is tentatively scheduled for February 2018.

Summary

This project will reconstruct the roadway to a two-lane, curb-and-gutter section with bike lanes and sidewalk on the south side from Capital Boulevard to New Bern Avenue.

Schedule

Project schedule with dates and descriptions
DateDescription
May 12, 2016Public Meeting
February 2018Public Meeting
Spring 2018Public Hearing
Fall 2018Complete Right of Way Acquisition
Fall 2018Advertise for Construction Contract
Winter 2019Award Construction Contract
Spring 2021Project Complete

History

The pavement along Yonkers Road has degraded and needs to be repaired to provide a more structurally sound corridor.

Was this page helpful?