Yonkers Road Improvements Project

Last updated Sep. 27, 2018 - 10:26 am
  • Planning
  • Design
  • Construction
  • Completed
  • Street Improvement Project
  • 14.9 Million
  • Roadway Design and Construction (Lead)
  • RK&K (Consultant)

Current Activity

Updated Aug. 31

The project is in the right of way and easement acquisition phase. The City is on schedule to advertise the project for construction bids in the spring of 2019.

Summary

This project will reconstruct the roadway to a two-lane, curb-and-gutter section with bike lanes and sidewalk on the south side from Capital Boulevard to New Bern Avenue.


Schedule

Project schedule with dates and descriptions
DateDescription
May 12, 2016Preliminary Plans Public Meeting (25% plan)
April 2018Design Plan Public Meeting (65% Plan)
Spring 2019Complete Right of Way Acquisition
Spring 2019Advertise for Construction Contract
Summer 2019Award Construction Contract
Summer 2019Pre-Construction Meeting
Fall 2021Project Complete

History

The pavement along Yonkers Road has degraded and needs to be repaired to provide a more structurally sound corridor.