Lake Dam Road Bridge Replacement

Last updated Jul. 31, 2019 - 2:37 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Bridge Replacement
  • About $2 million
  • Stormwater Management (Lead)
  • Dewberry Engineers, Inc. (Design)
  • S.T. Wooten Corporation (Construction)
  • SEPI Engineering and Construction, Inc.
  • Transportation Planning

Current Activity

Posted Wednesday, July 31

Construction is finished. We completed the final walkthrough with NCDOT this week. The road will reopen on Aug. 2 ahead of morning rush hour.

The contractor has:

  • Relocated water and gas mains across Walnut Creek (east of the new bridge);
  • Relocated the sewer main on the north side of the bridge;
  • Installed sediment and erosion control measures to protect the stream during construction;
  • Finished construction on the end and center support columns and concrete beams for the new bridge;
  • Finished the approach slabs for the new bridge, which provide a transition between the bridge and the roadway pavement;
  • Built bridge barriers (or parapets);
  • Added a sidewalk on the east side of the bridge; and,
  • Repaved the road.

The Public Utilities Department also completed emergency sewer repairs at the intersection of Lake Dam Road and Tryon Road.

Questions? Contact Gilles Bellot, PE, at 919-996-4001.

Summary

The 53-year-old bridge on Lake Dam Road is located over Walnut Creek just below the Lake Johnson dam. The purpose of this project is to replace the failing bridge structure so that it is safe to travel over.

Raleigh City Council approved the construction bid for this project on May 15. It was awarded to S.T. Wooten Corporation. SEPI Engineering and Construction, Inc., also will be handling inspections and materials testing for this project.

Construction documents were approved on Sept. 19 by the North Carolina Department of Transportation (NCDOT) and the construction contract with S.T. Wooten was finalized.

This is a joint project with NCDOT and the Federal Highway Administration.

Images

  • Lake Dam Road Bridge Complete
  • Lake Dam Road - Construction of New Bridge
  • Lake Dam Road - Construction
  • Lake Dam Road

Schedule

Project schedule with dates and descriptions
DateDescription
Fall 2017Easement acquisition and permitting process complete
Spring 2018Project design and construction bid complete
Fall 2018Project construction begins (Active construction work to start in January)
Summer 2019Project construction complete

History

This bridge was built in 1966. Over the years, the condition of the bridge declined making it unsafe to travel. The new bridge will address issues with the bridge structure while meeting current design standards. Lake Dam Road will reopen once the bridge is repaired.

Was this page helpful?

WalletHub named Raleigh

6th in List of Top 20 State Capitals to Live In

View our accolades >>