Fire Station 11 Renovation

Last updated Nov. 04, 2019 - 9:13 am
  • Planning
  • Design
  • Construction
  • Completed
  • City Facility - Fire
  • $2.1 million
  • Atlantic
  • Construction Management (Lead)
  • City of Raleigh Fire Department
  • Huffman Architects (Design)
  • Engineering Construction Company (Construction)

Current Activity

Posted Monday, Nov. 4

Engineering Construction Company (ECC) was awarded the construction contract for this project. Construction is about 98 percent complete. 

The contractor has: 

  • Worked on the foundation of the fire station; 
  • Built an apparatus bay; and, 
  • Finished interior renovations and the roof. 
Crews are now working on final items, like touching up the paint, checking equipment, bringing in furniture, cleaning, and finishing the landscaping. Work is expected to be done in early December. 

Summary

The purpose of this project is to make necessary renovations to Fire Station 11, which will include making improvements to the dormitory bay and bathrooms along with the dayroom bay. Renovations to the dayroom bay include the kitchen and watch room as well as expanding the two equipment bays to accommodate a larger ladder truck. Expansion of the equipment bays may include increasing the bay height.

Images

Fire Station 11 Rendering

Schedule

Project schedule with dates and descriptions
DateDescription
Spring 2017Project design begins
Summer 2018Project design complete
Late Fall 2018 Project construction begins
Late Fall 2019Project construction complete

History

Completing renovations to Fire Station 11 will help enhance the functionality of the station and allow for it to continually meet the growing needs of its service area.