Rocky_Branch_Open_Trench

Water and Sewer

State Street Water and Sewer Improvements Phase 3A

Upgrading downtown infrastructure

Construction is underway in downtown Raleigh to replace and upgrade aging water and sewer lines. This work is happening ahead of Bus Rapid Transit (BRT) construction in the area to avoid digging up the streets again later. Crews will replace or rehab nearly 2 miles of underground pipes across six downtown streets. Work is expected to finish Summer 2026. 

Benefits

  • Replaces aging water and sewer lines
  • Prepares streets for future Bus Rapid Transit (BRT) projects
  • Supports growth and reliability for years to come

Traffic Impacts

We know temporary lane closures and parking restrictions are not ideal for those who live, work, and play downtown. But replacing aging infrastructure now helps prevent emergency pipe breaks later, which would be a much bigger disruption.  

Completed Streets

Morgan Street - One minor repair needed

Current Impacts

E. Edenton Street (July 21-August 29, 2025)

  • 100–200 blocks between N. Wilmington Street and N. Person Street
  • Two travel lanes and street parking closed from 9 a.m. to 4 p.m.
  • One westbound lane open
  • Parking restrictions in designated areas
  • No planned water or sewer service interruptions 
To Be Completed
 
Street Name Work Hours Duration Estimated Dates
Wilmington Street Nights 7:00 PM - 6:00 AM 4 Months 9/2/25 - 12/30/25
Hargett Street Nights 7:00 PM - 6:00 AM 2 Months 1/5/26 - 2/27/26
New Bern Place Days 9:00AM - 4:00 PM 1 Month 3/2/26 - 3/31/26
Martin Street Nights 7:00 PM - 6:00 AM 1 Month 4/1/26 - 5/1/26
Blount Street Days 9:00AM - 4:00 PM 1 Month 5/4/26 - 6/8/26

All street impacts and work schedules are subject to change due to weather and other unforeseen events.

Phase 3a is one part of a larger, multi-phase project to upgrade water and sewer infrastructure across Raleigh. Future phases will continue improvements in other parts of the city. 

Project Details

 
Type:
Water and Sewer
Budget:
$10,000,000
Project Lead:
Todd Toler, Senior Engineer
Contractors:
Moffat Pipe, Inc.

Contact

 

Todd Toler
Senior Engineer
Phone: 919-996-3476 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Contractor Project Manager: 
Michael Tyler
Phone: 919-631-9814

Senior Project Manager:
Moffat Pipe
Brad Keeley
Phone: 919-710-5407

Raleigh Water On-site Inspector:
Kevin Radford
Phone: 919-795-0140
 

Lead Department:
Water
Participating Department:
Water
Service Unit:
Water and Sewer Development Review

Subscribe

 

Planning

Complete

Lead Department:
Water

Design

Complete

Lead Department:
Water

Construction

Moffat Pipe, Inc. began construction on June 9, 2025. The work includes replacing or rehabilitating about 3,700 feet of water lines, 6,100 feet of sewer mains, and 27 sewer manholes.

Weekly Update: 08/18 - 08/22:
Report from the project contractor. 

• An insertion valve was put in on Blount. 
• A point repair was completed on the 6” sewer on Edenton. 
• The Edenton water main was re-chlorinated, and a sample is being collected today, 8/18. 
• Excavation for the second Blount insertion valve was finished, and it's being installed today. 
• A fire hydrant was set up on Edenton.

Lead Department:
Water

Complete

Check back for future details.

Lead Department:
Water

Schedule

Project StageDate
Project Design CompleteSummer 2024
Permitting CompleteFall 2024
Easement Acquisition CompleteFall 2024
Project Bid CompleteFall 2024
Project Construction BeginsSummer 2025
Project Construction CompleteSummer 2026

Related Projects

  All projects