Mitchell Mill Road Widening Project

Last updated Apr. 25, 2018 - 1:41 pm
  • Planning
  • Design
  • Construction
  • Completed
  • Road Widening Project
  • $13.8 Millon
  • Roadway Design and Construction (Lead)
  • Kimley-Horn and Associates, Inc. (Design Consultant)
  • Rifenburg Construction (Construction Contractor)

Current Activity

Project Update, Updated April 25

Starting at 9 a.m., on Monday, April 30, crews will begin milling and paving operations at Singleleaf Lane. Flaggers will be on hand to direct traffic as needed, but there may be delays.

On Tuesday, May 1, starting at 9 a.m., Neuse Crossing Drive will be closed to traffic while the contractor removes the middle island at the entrance to Neuse Crossing Drive and completes milling and paving operations.

Forestville Road update:

The second half of the new box culvert is scheduled for installation in early June. During the second half of the box culvert installation, Forestville Road will be closed at Mitchell Mill Road. Mitchell Mill Road will remain open, but there will be no access to the northern section of Forestville Road from Mitchell Mill Road during this work.

The City will post more information once a firm date is established.

To stay up to date on the project, check the website often as pages will be updated regularly, or if you would like updates sent to your email, subscribe to project updates.

Summary

The project will widen Mitchell Mill Road between Louisburg Road and Forestville Road.

Street Improvements will include:

  • Four-lane median-divided road;
  • Curb and gutters;
  • Sidewalks;
  • Bike lanes;
  • Streetlights on both sides;
  • Turn-lane improvements;
  • Culvert replacement at the intersection of Mitchell Mill Road and Forestville Road;
  • A directional crossover at Neuse Crossing Drive and Longdale Drive;
  • Full access movements at Single Leaf Lane and Caliber Woods Drive; and,
  • New water main installation to connect existing sections currently installed along the corridor

Images

  • Existing Mitchell Mill Road
  • Visualization of proposed Mitchell Mill Road

Schedule

Project schedule with dates and descriptions
DateDescription
September 23, 2010Corridor Public Meeting
May 5, 2011Design Public Meeting
May 20, 2014Public Meeting
September 11, 2014Follow-up Public Meeting
December 2, 2014City Council Public Hearing
Fall 2015Complete Right of Way and Easement Acquisition
January 2016Advertise for Construction Contract
May 2016Award Construction Contract
Summer 2018Project Completion

History

Mitchell Mill Road Widening project is part of the 2005 Road Bond approved by voters of the City of Raleigh. Initial design funding for the project was authorized by the Raleigh City Council as part of the 2008-09 Capital Improvement Program.

Mitchell Mill Road is classified as a major thoroughfare in the City's 2030 comprehensive Plan. The existing roadway consists of primarily a two lane roadway with triple lefts at the Louisburg Road (US 401) intersection.

Existing Traffic Volume: 17,500 vehicles per day

Projected Traffic Forecast: 25,000 vehicles per day (2035)